Bayfield Mixed-Use

A 22-storey mixed-use tower with 240 apartments over a six-level retail and cinema podium.

240 Apartments
12,400 m² Retail
31 months Schedule
$167M Contract value

Highlights

What made this project work.

aria-hidden="true" focusable="false"

Jump-form core climbed ahead of flat-slab floors.

aria-hidden="true" focusable="false"

Cinema box isolated on elastomeric bearings.

aria-hidden="true" focusable="false"

Podium handed over six months before residential completion.

Schedule

Construction timeline.

Progress is computed from the phase data in src/data/projects.json. The overall progress bar at the top is the average of phase progress values.

Construction timeline

Sep 2023 — Oct 2026

Overall progress 63%
Sep 2023
Mar 2024
Sep 2024
Mar 2025
Jan 2026
Pre-construction Sep 2023 — Feb 2024
100%
Substructure & core Mar 2024 — Oct 2024
100%
Podium structure Sep 2024 — Apr 2025
80%
Tower & envelope Mar 2025 — Feb 2026
30%
Fit-out & handover Jan 2026 — Oct 2026
5%
View as table
Construction timeline phases
PhaseStartEndProgress
Pre-constructionSep 2023Feb 2024100%
Substructure & coreMar 2024Oct 2024100%
Podium structureSep 2024Apr 202580%
Tower & envelopeMar 2025Feb 202630%
Fit-out & handoverJan 2026Oct 20265%