public Completed central
Greenfield School Campus
A 1,400-student secondary school with a sports hall, performing arts block and a central quad.
1,400 Students
18,200 m² Floor area
18 months Schedule
$54M Contract value
Highlights
What made this project work.
Two-stage handover aligned with the academic year.
Cross-laminated timber sports hall roof.
Photovoltaic array covers 35% of annual energy use.
Schedule
Construction timeline.
Progress is computed from the phase data in src/data/projects.json. The overall progress bar at the top is the average of phase progress values.
Construction timeline
Sep 2017 — Aug 2019
Overall progress 100%
Sep 2017
Feb 2018
Jun 2018
Nov 2018
May 2019
Pre-construction Sep 2017 — Jan 2018
Substructure & slab Feb 2018 — Jun 2018
Structure & envelope Jun 2018 — Dec 2018
MEP & fit-out Nov 2018 — May 2019
Handover & opening May 2019 — Aug 2019
View as table
| Phase | Start | End | Progress |
|---|---|---|---|
| Pre-construction | Sep 2017 | Jan 2018 | 100% |
| Substructure & slab | Feb 2018 | Jun 2018 | 100% |
| Structure & envelope | Jun 2018 | Dec 2018 | 100% |
| MEP & fit-out | Nov 2018 | May 2019 | 100% |
| Handover & opening | May 2019 | Aug 2019 | 100% |
More in this sector
Related projects.
public Completed
Central Civic Hall
A 4,200-seat civic hall and council chamber with a mass-timber roof and a public forecourt.
- Location
- Riverton
- Value
- $78M
- Year
- 2021
public Completed
Summit Medical Campus
A 280-bed acute-care hospital with an attached outpatient pavilion and a central energy plant.
- Location
- Riverton
- Value
- $263M
- Year
- 2023