Ashford Port Expansion

A new container terminal with 1.1 km of quay, four ship-to-shore cranes and an automated stacking yard.

1,100 m Quay length
4 Cranes
42 months Schedule
$412M Contract value

Highlights

What made this project work.

aria-hidden="true" focusable="false"

Quay wall built from precast concrete caissons.

aria-hidden="true" focusable="false"

Automated stacking yard requires dedicated commissioning window.

aria-hidden="true" focusable="false"

Dredging programme consented under a separate permit.

Schedule

Construction timeline.

Progress is computed from the phase data in src/data/projects.json. The overall progress bar at the top is the average of phase progress values.

Construction timeline

Jun 2026 — Sep 2029

Overall progress 0%
Jun 2026
Feb 2027
Oct 2027
Jun 2028
Mar 2029
Pre-construction Jun 2026 — Jan 2027
0%
Dredging & caissons Feb 2027 — Dec 2027
0%
Quay & pavements Oct 2027 — Aug 2028
0%
Cranes & systems Jun 2028 — Apr 2029
0%
Commissioning & handover Mar 2029 — Sep 2029
0%
View as table
Construction timeline phases
PhaseStartEndProgress
Pre-constructionJun 2026Jan 20270%
Dredging & caissonsFeb 2027Dec 20270%
Quay & pavementsOct 2027Aug 20280%
Cranes & systemsJun 2028Apr 20290%
Commissioning & handoverMar 2029Sep 20290%