industrial Planned east
Ashford Port Expansion
A new container terminal with 1.1 km of quay, four ship-to-shore cranes and an automated stacking yard.
1,100 m Quay length
4 Cranes
42 months Schedule
$412M Contract value
Highlights
What made this project work.
Quay wall built from precast concrete caissons.
Automated stacking yard requires dedicated commissioning window.
Dredging programme consented under a separate permit.
Schedule
Construction timeline.
Progress is computed from the phase data in src/data/projects.json. The overall progress bar at the top is the average of phase progress values.
Construction timeline
Jun 2026 — Sep 2029
Overall progress 0%
Jun 2026
Feb 2027
Oct 2027
Jun 2028
Mar 2029
Pre-construction Jun 2026 — Jan 2027
Dredging & caissons Feb 2027 — Dec 2027
Quay & pavements Oct 2027 — Aug 2028
Cranes & systems Jun 2028 — Apr 2029
Commissioning & handover Mar 2029 — Sep 2029
View as table
| Phase | Start | End | Progress |
|---|---|---|---|
| Pre-construction | Jun 2026 | Jan 2027 | 0% |
| Dredging & caissons | Feb 2027 | Dec 2027 | 0% |
| Quay & pavements | Oct 2027 | Aug 2028 | 0% |
| Cranes & systems | Jun 2028 | Apr 2029 | 0% |
| Commissioning & handover | Mar 2029 | Sep 2029 | 0% |
More in this sector
Related projects.
industrial Completed
Westport Logistics Hub
A 92,000 m² distribution centre with 56 dock doors, a 14 MW rooftop PV array and an automated sortation mezzanine.
- Location
- Bayfield
- Value
- $142M
- Year
- 2024
industrial In progress
Ridgeline Data Center
A 24 MW hyperscale data centre with a 2N power architecture and a closed-loop cooling system.
- Location
- Bayfield
- Value
- $310M
- Year
- 2026