Ridgeline Data Center

A 24 MW hyperscale data centre with a 2N power architecture and a closed-loop cooling system.

24 MW IT load
11,400 m² White space
26 months Schedule
$310M Contract value

Highlights

What made this project work.

aria-hidden="true" focusable="false"

Phased commissioning of two 12 MW halls.

aria-hidden="true" focusable="false"

Closed-loop cooling reduces site water use by 70%.

aria-hidden="true" focusable="false"

Pre-fabricated switchgear modules craned into position.

Schedule

Construction timeline.

Progress is computed from the phase data in src/data/projects.json. The overall progress bar at the top is the average of phase progress values.

Construction timeline

Feb 2024 — Jun 2026

Overall progress 59%
Feb 2024
Aug 2024
Jan 2025
Jul 2025
Jan 2026
Pre-construction Feb 2024 — Jul 2024
100%
Substructure & slab Aug 2024 — Feb 2025
100%
Structure & envelope Jan 2025 — Sep 2025
65%
MEP & switchgear Jul 2025 — Feb 2026
25%
Commissioning & handover Jan 2026 — Jun 2026
5%
View as table
Construction timeline phases
PhaseStartEndProgress
Pre-constructionFeb 2024Jul 2024100%
Substructure & slabAug 2024Feb 2025100%
Structure & envelopeJan 2025Sep 202565%
MEP & switchgearJul 2025Feb 202625%
Commissioning & handoverJan 2026Jun 20265%