industrial In progress west
Ridgeline Data Center
A 24 MW hyperscale data centre with a 2N power architecture and a closed-loop cooling system.
24 MW IT load
11,400 m² White space
26 months Schedule
$310M Contract value
Highlights
What made this project work.
Phased commissioning of two 12 MW halls.
Closed-loop cooling reduces site water use by 70%.
Pre-fabricated switchgear modules craned into position.
Schedule
Construction timeline.
Progress is computed from the phase data in src/data/projects.json. The overall progress bar at the top is the average of phase progress values.
Construction timeline
Feb 2024 — Jun 2026
Overall progress 59%
Feb 2024
Aug 2024
Jan 2025
Jul 2025
Jan 2026
Pre-construction Feb 2024 — Jul 2024
Substructure & slab Aug 2024 — Feb 2025
Structure & envelope Jan 2025 — Sep 2025
MEP & switchgear Jul 2025 — Feb 2026
Commissioning & handover Jan 2026 — Jun 2026
View as table
| Phase | Start | End | Progress |
|---|---|---|---|
| Pre-construction | Feb 2024 | Jul 2024 | 100% |
| Substructure & slab | Aug 2024 | Feb 2025 | 100% |
| Structure & envelope | Jan 2025 | Sep 2025 | 65% |
| MEP & switchgear | Jul 2025 | Feb 2026 | 25% |
| Commissioning & handover | Jan 2026 | Jun 2026 | 5% |
More in this sector
Related projects.
industrial Completed
Westport Logistics Hub
A 92,000 m² distribution centre with 56 dock doors, a 14 MW rooftop PV array and an automated sortation mezzanine.
- Location
- Bayfield
- Value
- $142M
- Year
- 2024
industrial Planned
Ashford Port Expansion
A new container terminal with 1.1 km of quay, four ship-to-shore cranes and an automated stacking yard.
- Location
- Ashford
- Value
- $412M
- Year
- 2028