infrastructure In progress east
Eastline Light Rail Extension
An 8.6 km light rail extension with seven stops, a depot stub and three new traction substations.
8.6 km Length
7 Stops
34 months Schedule
$218M Contract value
Highlights
What made this project work.
Block possession windows negotiated with the operator.
Depot stub future-proofed for a 14-vehicle fleet.
Traction substations commissioned under live-line permits.
Schedule
Construction timeline.
Progress is computed from the phase data in src/data/projects.json. The overall progress bar at the top is the average of phase progress values.
Construction timeline
Jul 2023 — Sep 2026
Overall progress 55%
Jul 2023
Feb 2024
Nov 2024
Aug 2025
Mar 2026
Pre-construction Jul 2023 — Jan 2024
Utilities & track slab Feb 2024 — Dec 2024
Stops & systems Nov 2024 — Aug 2025
Testing & commissioning Aug 2025 — Apr 2026
Trial service & handover Mar 2026 — Sep 2026
View as table
| Phase | Start | End | Progress |
|---|---|---|---|
| Pre-construction | Jul 2023 | Jan 2024 | 100% |
| Utilities & track slab | Feb 2024 | Dec 2024 | 100% |
| Stops & systems | Nov 2024 | Aug 2025 | 60% |
| Testing & commissioning | Aug 2025 | Apr 2026 | 15% |
| Trial service & handover | Mar 2026 | Sep 2026 | 0% |
More in this sector
Related projects.
infrastructure Completed
Northgate Bridge Widening
Widening of a 1.2 km river crossing from four to six lanes with a separated transitway and a shared-use path.
- Location
- Port Marin
- Value
- $96M
- Year
- 2022
infrastructure Completed
Ridgeline Reservoir
A 24,000 ML raw-water reservoir with a 38 m earthfill embankment and a morning-glory spillway.
- Location
- Bayfield
- Value
- $88M
- Year
- 2022