Eastline Light Rail Extension

An 8.6 km light rail extension with seven stops, a depot stub and three new traction substations.

8.6 km Length
7 Stops
34 months Schedule
$218M Contract value

Highlights

What made this project work.

aria-hidden="true" focusable="false"

Block possession windows negotiated with the operator.

aria-hidden="true" focusable="false"

Depot stub future-proofed for a 14-vehicle fleet.

aria-hidden="true" focusable="false"

Traction substations commissioned under live-line permits.

Schedule

Construction timeline.

Progress is computed from the phase data in src/data/projects.json. The overall progress bar at the top is the average of phase progress values.

Construction timeline

Jul 2023 — Sep 2026

Overall progress 55%
Jul 2023
Feb 2024
Nov 2024
Aug 2025
Mar 2026
Pre-construction Jul 2023 — Jan 2024
100%
Utilities & track slab Feb 2024 — Dec 2024
100%
Stops & systems Nov 2024 — Aug 2025
60%
Testing & commissioning Aug 2025 — Apr 2026
15%
Trial service & handover Mar 2026 — Sep 2026
0%
View as table
Construction timeline phases
PhaseStartEndProgress
Pre-constructionJul 2023Jan 2024100%
Utilities & track slabFeb 2024Dec 2024100%
Stops & systemsNov 2024Aug 202560%
Testing & commissioningAug 2025Apr 202615%
Trial service & handoverMar 2026Sep 20260%