infrastructure Completed west
Ridgeline Reservoir
A 24,000 ML raw-water reservoir with a 38 m earthfill embankment and a morning-glory spillway.
24,000 ML Capacity
38 m Embankment
20 months Schedule
$88M Contract value
Highlights
What made this project work.
Embankment built from locally won fill with quality-control grouting.
Morning-glory spillway cast in three lifts.
Reservoir filling sequenced over two wet seasons.
Schedule
Construction timeline.
Progress is computed from the phase data in src/data/projects.json. The overall progress bar at the top is the average of phase progress values.
Construction timeline
Jul 2020 — Nov 2022
Overall progress 100%
Jul 2020
Feb 2021
Jul 2021
Feb 2022
Aug 2022
Pre-construction Jul 2020 — Jan 2021
Foundation & grouting Feb 2021 — Aug 2021
Embankment Jul 2021 — Apr 2022
Spillway & outlet Feb 2022 — Aug 2022
Commissioning & handover Aug 2022 — Nov 2022
View as table
| Phase | Start | End | Progress |
|---|---|---|---|
| Pre-construction | Jul 2020 | Jan 2021 | 100% |
| Foundation & grouting | Feb 2021 | Aug 2021 | 100% |
| Embankment | Jul 2021 | Apr 2022 | 100% |
| Spillway & outlet | Feb 2022 | Aug 2022 | 100% |
| Commissioning & handover | Aug 2022 | Nov 2022 | 100% |
More in this sector
Related projects.
infrastructure Completed
Northgate Bridge Widening
Widening of a 1.2 km river crossing from four to six lanes with a separated transitway and a shared-use path.
- Location
- Port Marin
- Value
- $96M
- Year
- 2022
infrastructure In progress
Eastline Light Rail Extension
An 8.6 km light rail extension with seven stops, a depot stub and three new traction substations.
- Location
- Ashford
- Value
- $218M
- Year
- 2026